The construction of two new extensions, one to form
a new entrance including a head teacher's office and reception
area, the other to form three additional classrooms, a science lab
and additional toilet facilities.
Both extensions were built using piled foundations
and cavity block work walls with Western Red Cedar cladding. The
roof was steel framed with curved beams and covered with a Protan
Roof Covering System. An underfloor heating system was installed
to the rear extension and a central feature hexagonal rooflight was
formed to the centre of the rear extension.
External works included the forming of a new ball
court and hard landscaping.